Drop the Overtime AddOn on a position, set the standard day and the hours above it on the slider, and Splinde works the hourly cost out of the position's own fee. Then choose how the days run: Simple prices every day on the line as a long day, Individual charges overtime only on the days that run long. Because the AddOn sits on the line, the number moves whenever the fee or the day count moves.
Set the rates
Open the sidebar Insert tab, then the AddOns sub-tab, and drag the card titled Overtime onto the Cost Item.
Expand the strip. Under Set the Overtime Rates a slider labelled Base h marks the standard day, which is the first section of the slider. A new Overtime AddOn starts with a standard day of 8 hours and one section above the Base of 2 hours, ending at 10 hours, at 0 percent.
Drag a handle, or type into the numeric field above a section, to set how many hours that section is long. Later sections move along with it. Hover between two handles and click the + to split off a new section.
Enter the uplift percentage in the field below each section above the Base. The standard day is never charged as overtime.
The AddOn starts charging as soon as the rates are entered, and the line total, the Section subtotal and the budget Total follow.
Simple or Individual
The mode button sits at the start of the AddOn's sentence line and reads either Simple or Individual. Click it to switch.
Simple assumes every day on the line runs to the end of the last section above the Base. Use it before the shoot, to show the client what a long day costs, for a worst case, or for a deal memo that prices a long day flat across the whole shoot.
Individual follows the days as they are planned or as they ran. Use it as soon as the days differ:
Click the mode button until it reads Individual. A second section appears, Set the Overtime Hours for individual Days, with a slider labelled Days.
Split the day count into blocks the way you split the hours on the slider: hover between handles, click the +, then drag the handles to set where each block ends.
Enter the hours worked for each block. Only a block that reaches a section above the Base pays for it.
How the number is worked out
The hourly rate is Amount multiplied by Fee, divided by the hours of the standard day. Each section above the Base costs that hourly rate, multiplied by the hours in that section, multiplied by one plus that section's percentage. Simple charges that for every day on the line; Individual charges it for each day in a block whose hours reach that section.
An example. One person, five days, Fee 800. The standard day ends at 8 hours and one section above the Base runs to 12 hours at 50 percent. The hourly rate is 800 divided by 8, which is 100, so four overtime hours cost 4 times 100 times 1.5, or 600 on a long day.
Simple charges those four hours on all five days: 3,000.
Individual, with a two-day block at 12 hours and a three-day block at 8 hours, charges the two long days only: 1,200.
Good to know
Simple and Individual are the Overtime AddOn's own two modes. Percentage AddOns such as a markup have a different pair, Unified and Individual, which choose one rate for everything or a separate rate for each.
On a Production Cost Item the AddOn works on Prep, Day and Wrap together. In Individual mode, lay the blocks out in the order the schedule runs, so a block at the front of the timeline is prep.
The Days slider runs as far as the Cost Item's own day count. When the schedule grows, raise the day count and extend the blocks to match.
Hours are whole numbers, and the slider runs up to 18 hours. The rate slider starts three hours below the end of the standard day.
The per-hour caption inside the AddOn shows Fee divided by the standard day. With Amount above 1, read it as a rate per unit and read the section figures as totals for the whole line.